On December 24, 2025, the first "vertical air-supported structure" foundation pit air membrane in China's construction industry was completed in the Wangfujing Foreign Language Bookstore upgrade and renovation project.

Located in the heart of the Wangfujing commercial district, adjacent to important buildings such as the Muslim Building and the No. 3, Jia, Caichang Hutong courtyard house, the project faced extremely stringent construction requirements due to its cramped site and complex community conditions. To minimize the impact of the excavation work on the surrounding commercial area, the district's Housing and Construction Commission, in conjunction with local authorities and relevant departments, coordinated the construction of the air-supported membrane structure.
The project has a planned total land area of 1854.91 square meters, requiring full air-supported membrane coverage. The logistics channel has a net width of only 4000mm, requiring a 3750mm vehicle passage width, and the loading area, while limited, must meet a 14-meter clearance height, posing significant challenges to the air-supported membrane construction.
After nearly two months and 16 rounds of consultations and demonstrations, the construction team innovatively adopted a construction combination scheme of "primarily fixing to the original walls, supplemented by cast-in-place ground beams, and constrained by a cage-type steel structure." This approach ensured the required clearance height for the air-supported membrane while effectively controlling membrane deformation caused by external factors such as rain, snow, and wind, ensuring the safety and stability of the air-supported membrane structure. Currently, the air-supported membrane structure is undergoing continuous optimization and adjustment, and the internal lighting and intelligent control equipment are being simultaneously debugged. The final acceptance inspection will be carried out according to regulations. The air-supported membrane for this foundation pit is scheduled to officially open on January 1, 2026.
This innovative application of the air-supported membrane in this project represents a breakthrough in green construction in the complex environment of the capital's core area. The fully enclosed structure of the air-supported membrane can block more than 95% of construction dust and reduce operating noise to below 50 decibels. The all-weather operation capability of the air-supported membrane reduces the impact of weather on construction by more than 90%, shortening the overall construction period by approximately 20%. It provides a replicable green construction solution for building renovation in the core area of megacities.
Our company provides interlocking doors for personnel access and safety doors. The personnel doors feature double-sided interlocking to ensure the airtightness of the membrane, while the safety doors provide emergency escape routes within the membrane.

Interlocking doors for personnel access


The successful implementation of this project has filled the technical gaps in China regarding the anchoring of air-supported membrane structures for foundation pits on irregular sites and the calculation of complex load combinations. It has provided practical evidence for green construction in subsequent similar projects within the region and set a new benchmark for the deep integration of urban renewal and green building.